dspTrack
Plan Task Dependency
Use this page to Add a Predecessor Task.
To access this page:
- Select Track > Project from the Navigation pane.
- Click Plans for a project.
- Click Tasks for a plan.
- Click Predecessor Tasks for a task.
Field |
Description |
PREDECESSOR PLAN ID |
Displays the name of the plan containing the task that is the predecessor in the dependency relationship. |
IS COMPLETED |
If enabled, work on the predecessor task has completed. |
PREDECESSOR PLAN TASK ID |
Displays the name of the task that is the predecessor in the dependency relationship. |
DEPENDENCY TYPE ID |
Displays the Dependency Type of the dependency relationship. Values are:
Refer to Use Dependency Types for more information. |
SUCCESSOR PLAN ID |
Displays the name of the plan containing the task that is the successor in the dependency relationship. NOTE: View a list of all successor tasks for the selected task on the Project Task Successor Dependency page (Project > Plans > Plan Tasks > Vertical View for a Plan Task > Additional Information tab > Successor Tasks). |
SLACK |
Displays a number used with the SLACK UOM to determine the amount of time that has to pass before a successor task can start or finish after its predecessor starts or finishes. |
SUCCESSOR PLAN TASK ID |
Displays the name of the task that is the successor in the dependency relationship. |
SLACK UOM |
Displays an option used with SLACK to determine the amount of time that has to pass before a successor task can start or finish after its predecessor starts or finishes. Values are Day(s), Hour(s), Minute(s), Month(s), and Week(s). |